ANALYSIS OF HEAT CONSUMPTION OF PRODUCTION BUILDINGS BARLINEC INVEST LLC

Authors

DOI:

https://doi.org/10.31649/2311-1429-2019-1-120-126

Keywords:

technological heat consumption, heat losses for heating and ventilation, heat losses on heating of aspiration air, heat generation

Abstract

The report presents an analysis of thermal energy efficiency at Barlinek-Invest LLC. The analysis of heat consumption for production needs, heating and ventilation and heat generation for the warm and cold periods.

Barlinek Group is a leading global manufacturer of multilayer wood floors with an annual production capacity of more than 12 million m2. The most important product of the commercial offer is Barlinek parquet board - a multilayer floor made from the best types of wood from European and exotic species. Gender is sold in 64 countries on 6 continents.

In addition to parquet boards, the Barlinek Group produces certified floors for sports facilities, floor skirting boards and biofuels widely known for their high quality: pellets and briquettes for fireplaces.

Barlinek attaches great importance to the fact that the technologies that are used and the products that are produced at the group's factories are ecological and environmentally friendly.

Thanks to continuous modernization of production and investments in modern technologies of the Barlinek group of companies, they are one of the cleanest industries in their industry in Poland and Europe. The activities of Barlinek company show that environmental protection can be not only obligations stipulated by the legislation of the respective countries for enterprises, but also an important element of a long-term development strategy.

The buildings of the department for the manufacture of fuel pellets and the woodworking workshop are characterized by the lack of compensation of aspiration air by supply ventilation and insufficient heating equipment, which leads to a decrease in the internal temperature in them.

The total heat consumption capacity in the current state for the cold period is 21.05 MW, that is, the existing heat capacity of the boiler house, which is 18.4 MW, is not enough.

Author Biographies

Igor Ponomarchuk, Vinnytsia National Technical University

Candidate of Technical Sciences, Associate Professor of the Department of Engineering Systems in Construction

Natalia Slobodian, Vinnytsia National Technical University

Candidate of Science (Engineering), Associate Professor, Department of Engineering Systems in Construction

References

DSTU 4714:2007 «Énerhosberezhenye.Toplyvno-énerhetycheskyy balans promyshlennykh predpryyatyy. Metodyka postroenyya y analyza».

DBN V.2.5-67:2013. Opalennya, ventylyatsiya ta kondytsionuvannya povitrya. – K.: Minrehionbud, 2013. – 141 s.

Downloads

Abstract views: 16

Published

2019-08-12

How to Cite

[1]
I. Ponomarchuk and N. Slobodian, “ANALYSIS OF HEAT CONSUMPTION OF PRODUCTION BUILDINGS BARLINEC INVEST LLC”, СучТехнБудів, vol. 26, no. 1, pp. 120–126, Aug. 2019.

Issue

Section

ENGINEERING SYSTEMS OF BUILDINGS

Metrics

Downloads

Download data is not yet available.